Temporary Closures

Construction is staged in an effort to minimize closures and detours. Please note there are additional temporary closures and detours planned later in the project. Please check back for detours in years 2019 and 2020.


The maps below show the signed detours for 2018 and the first quarter of 2019.

Highway 101 On-Ramp at Casitas Pass

The Highway 101 southbound on-ramp at Casitas Pass Road will be closed for 2 weeks in 2018. Detour signs will direct motorists to enter southbound Highway 101 at the on-ramp at Bailard Avenue.

Linden Avenue & Ogan Road

The Linden Avenue Overcrossing will be closed to vehicles for 3 weeks in 2018. Pedestrians and bicycles will be able to use the overcrossing for most of the closure. Vehicles will be directed to Foothill Road, Ogan Road, Casitas Pass Road, and Carpinteria Avenue during the closure

Via Real

Via Real north of Casitas Pass Road will be closed for 1 month in 2018. A detour will be in place along Casitas Pass Road, Carpinteria Avenue, and Linden Avenue

Highway 101 Southbound Off-ramp at Casitas Pass Road

The Highway 101 southbound off-ramp at Casitas Pass Road will close for 1 month in 2018. A detour will be in place along Linden Avenue, Carpinteria Avenue, and Casitas Pass Road.

Highway 101 Off-ramp at Linden Avenue

The Highway 101 off-ramp at Linden Avenue will be closed for 6 months in 2018 and 2019. Vehicles can use the Highway 101 off-ramps at Reynolds Avenue and Casitas Pass Road as detours.

Carpinteria Creek Bikeway

The bikeway along Carpinteria Creek will close for bridge work for 5 months in 2018. The bike lane and sidewalk on the new Via Real connection will serve as an alternate route.