Project Overview
Highway 101: Summerland added a peak-period carpool lane in each direction for 1.7 miles. The new lanes opened in conjunction with the end of construction of the Highway 101: Padaro segment since Summerland is located between two construction areas.
At the Evans Avenue Undercrossing, a new bridge segment connects the freeway bridges and is accompanied by pedestrian, bike lane, and lighting improvements underneath Highway 101.
At the Sheffield Drive Interchange, new freeway bridges were built along with new right hand on- and off-ramps on southbound Highway 101 and improved northbound on- and off-ramps. The on-ramp at Wallace Avenue was replaced and a new retaining wall was added to accommodate the wider freeway.
There are also two new sound walls. Planting and irrigation have been installed and the plant establishment period continues.